In mid-October, an Our Town photographer caught a dog walker turning back at a fresh barrier at East 78th Street on the East River Esplanade. Our Town reported that the barrier had nothing to do with the hospital construction that has kept this part of the waterfront closed since 2022. NYC Parks had started repairing a sinkhole near East 80th Street, and that work closed the entrances at 78th and 81st Streets. It also pushed back the reopening of the blocks to the south. Hospital for Special Surgery's work on the East 70s is nearly finished. Across the rest of the Upper East Side waterfront, the remaining closures come from the ground under the path and from a city repair program scheduled into 2028.
Here is the path from south to north as of this week, and who controls each section.
| Stretch | Where it stands | Who sets the timing |
|---|---|---|
| East 53rd to 60th Street, East Midtown Greenway and Andrew Haswell Green Park Phase 2B | Open, including the 60th Street ramp | NYCEDC, finished new construction |
| East 70th to 71st Street, with the 71st Street ramp | Open, ramp since June 2026 | HSS, work completed |
| East 72nd to 78th Street | Closed; reopening expected Monday, November 23 | HSS contractor, timed around Parks sinkhole work |
| 78th and 81st Street entrances | Closed in mid-October for sinkhole repairs near 80th Street | NYC Parks |
| East 90th Street | NYC Ferry landing on the Astoria route at East 90th Street and FDR Drive | NYC Ferry |
| East 93rd to 96th Street | Sinkhole closure in April; repair closure planned from May 26 | NYC Parks |
| East 94th to 105th Street, Bobby Wagner Walk | Plan reduced to sinkhole repairs and stabilization | NYC Parks |
What HSS owed the waterfront, and what it's handing back
Our Town reports that the nine-block closure starting at East 70th Street began in 2022, when HSS started building Kellen Tower, its new wing next to the FDR. The tower cost nearly $300 million and was finished this summer. The hospital still had to rebuild the esplanade alongside it. HSS's project page says the work covers East 70th to East 78th Street, is coordinated with NYC Parks and the Department of Transportation, and follows the city's master plan for the esplanade. It builds on a $1.8 million renovation HSS did between East 70th and 72nd Streets in 2018.
The first piece reopened earlier this year. The 70th to 71st Street section now has permanent pavers and landscaping, two sinkholes repaired by NYC Parks, and a Con Edison fuel line taken out of service and removed. The new permanent pedestrian ramp at 71st Street opened in June 2026. HSS leaders marked the occasion with City Council Speaker Julie Menin and Parks Commissioner Tricia Shimamura. Our Town notes that Shimamura lives in the area and used to chair Community Board 8's parks committee. At that reopening she told the paper her agency was "all about a contiguous waterfront that is open and accessible to the public."
The East 72nd to 78th Street section comes next. HSS lists new pavers, landscaping, fitness equipment, structural repairs to the seawall, and a repaired sinkhole at the foot of the East 78th Street ramp. A separate sinkhole at East 74th Street, fixed by NYC Parks, is already done. Patch reported that the section will also be painted. Jennifer Ratner, board chair of Friends of the East River Esplanade, told Our Town she was looking forward to the fitness equipment in particular.
A sinkhole at 80th Street set the reopening date
HSS first expected to reopen everything through East 78th Street by the end of October. Tracy Hickenbottom, HSS's assistant vice president of public relations, explained the change to Patch: "additional sinkhole repairs being undertaken by NYC Parks near East 80th Street require access to a portion of the construction area, affecting the schedule."
The Parks repair is a few blocks north of the HSS site, but its crews and equipment have to come in through the HSS work zone. In an email to Friends of the East River Esplanade that Our Town reviewed, Steve Simon, chief of staff for the Parks Department's Manhattan office, described it this way: "Access is being provided through the area directly to the south where HSS' contractor has been working, disrupting their schedule." He added that the contractor now expected to finish the surface improvements the week of November 23, "at which time the section of the esplanade between 72nd - 78th Streets will be open to the public."
The October work began on October 13, a few days after Parks had predicted the closed section would reopen by the end of the month. It closed the pedestrian entrances at East 78th and East 81st Streets, and Simon wrote that signs would be posted about the closures. On October 15, Patch reported that the 80th Street sinkhole work was expected to take about two weeks. Ratner called the whole process "one delay after another" and told Our Town that the closure comes up whenever she talks with neighbors. The Friends group's website has also pushed for a faster reopening of the East 70s and objected that no temporary route was provided during construction.
The same problem keeps turning up in the 90s
The 80th Street repair is one of several this year. On April 23, a growing sinkhole between East 93rd and 94th Streets forced a sudden closure to both pedestrians and cyclists starting around 8 a.m., Patch reported. Ratner told Patch the closure disrupted commutes and pointed to repairs the city had put off. That stretch reopened on April 30, after engineers approved moving the fence, but the sinkhole itself stayed fenced off while Parks looked at a permanent fix, Our Town reported. In May, Friends told Our Town it expected a repair closure from East 93rd to East 96th Street starting May 26 and lasting about four weeks.
Just north of there, plans for the Bobby Wagner Walk have been scaled back. In July, Patch reported that the East 94th to 105th Street segment will get sinkhole repairs and stabilization rather than the full reconstruction that had been promised, and that the $294 million project was being cut down. CIVITAS representatives told Patch that local groups were not consulted before the change. In October, Our Town reported that rebuilding East 94th to 107th Street could cost well over $500 million and remains on hold until funding is found.
The Parks schedule after November 23
Even after the HSS section reopens, the Upper East Side waterfront is still inside active city projects. NYC Parks' capital project tracker lists two:
- Phase 2, East 96th to 125th Street. Active construction, $47.804 million in funding, projected completion in August 2027.
- Phase 3, East 63rd to 81st Street and East 90th to 125th Street, among other locations. Active construction, $85.183 million in funding, projected completion in April 2028.
Phase 3's range, 63rd to 81st Street, includes the blocks HSS is about to reopen and the 80th Street sinkhole site. The tracker lists the project by street range and gives no block-by-block schedule. Phase 2 and Phase 3 each have a public tracker page that shows progress and a projected completion date.
South of 63rd, the work is already done
The southern end shows what a finished section looks like. The East Midtown Greenway and Andrew Haswell Green Park Phase 2B, from East 53rd to 60th Street, are open. The northern part of that esplanade opened in 2023. NYCEDC's opening announcement puts the city's combined investment at $197.6 million. Of that, $42.6 million went to Phase 2B, which renovated the East 60th Street ramp and added a new lawn, landscaping, lighting, and seating.
That southern stretch was built as new construction. From 70th Street north, the remaining work is repair: seawalls, sinkholes, and a fuel line already taken out under 71st Street. The section HSS expects to reopen on Monday, November 23, runs from East 72nd to East 78th Street and will have new pavers, plantings, and fitness equipment. North of 78th, gaps on the path will depend on how Parks schedules its sinkhole repairs.
If the esplanade is part of why you live on the far East Side, or a reason you're considering it, the details above affect what a block is like to live on. The Torsiello Team follows these block-level changes across Manhattan and Brooklyn. If you're weighing a move near York Avenue or the FDR, Contact Michael.